Project Status Reports
Events Planning, Scheduling and Communication
- Phase 1—standardizing the scheduling process. Completed May ‘06.
- Phase 2—updating of outdated Facilities put on hold, should be completed by FY 2007.
- Phase 3—coordination of information into Banner. Working with Jim Cotton and Jamie Desjardin. This part of the project is scheduled to be completed by December ‘06 instead of September ‘07