Dimitry Renovation Weekly Updates

Each week, members of the Division of Capital Asset Management and Maintenance (DCAMM), Perry Dean Rogers Partners Architects, and G&R Construction meet with NECC staff to review project timelines, provide updates, and finalize plans. Please see the most recent updates below:

 

Weekly Update: May 14, 2018

The summer semester has begun, and parking remains available for students, faculty, and staff with a valid NECC parking decal in Lot A. Please continue to be aware and use caution when entering and exiting Lot A. With questions related to parking, or progress of the renovations, please email dimitryrenovations@necc.mass.edu.

Weekly Update: May 7, 2018

Contractors, DCAMM, Perry Dean Rogers, and Northern Essex Facilities staff continue to meet and discuss project timelines as well as share updates on the on-going exterior renovations. With finals approaching and the spring semester coming to a close, parking remains available for students, faculty, and staff with a valid NECC parking decal in Lot A. Please continue to be aware and use caution when entering and exiting Lot A.

 

Weekly Update: April 30, 2018

Progress continues to be made on the exterior of the Dimitry building.  Contractors are at the site on a daily basis as the project continues to move ahead.  For weekly photo updates, please visit the “View Construction Progress” page.

If you have any questions or comments please email: dimitryrenovations@necc.mass.edu.

Weekly Update: April 23, 2018

NECC facilities staff will hang additional signage regarding parking and entrance/exits to assist with the flow of traffic in and out of Lot A. These signs will also help direct street traffic to the new entrance/exit located on Common Street. Additionally, a sign will be hung on the temporary construction fence reminding students, staff, and visitors that all NECC-related business should be directed to 414 Common Street.

 

 Weekly Update: April 17, 2018

Construction and demolition continues on the exterior of the Dimitry building.  Additional signage for parking and entrance/exits will be hung to assist with the flow of traffic in and out of Lot A.

Parking in Lot A remains available for students, faculty, and staff with a valid NECC parking decal. Please continue to be aware and use caution when entering and exiting Lot A.

 

Weekly Update: April 9, 2018

G&R Construction continues to make progress in the demolition of the Dimitry building and the removal of the existing front entranceway. Construction and project signs will be hung on the temporary fencing this week.  Parking remains available for students, faculty, and staff with a valid NECC parking decal in Lot A. Please continue to be aware and use caution when entering and exiting Lot A.

Weekly Update: April 2, 2018

Demolition has officially begun! The quad area in front of the Dimitry entrance has been dug up, and the existing concrete has been removed.  The area inside the construction fence is a hard hat area; therefore, the use of hard-hats will be strictly enforced. For weekly photo updates, please visit the “View Construction Progress” page.

 

Weekly Update: March 26, 2018

The area inside the construction fence is now a hard hat area, and is regulated by OSHA’s “head protection” mandates, which require a hard hat to be worn by anyone who enters.  No NECC persons are permitted to enter the hard-hat area.

Any and all college-related business such as admissions, campus tours, inquiries about classes, payments, etc., will be directed to 414 Common St.

The entrance/exit to the Dimitry parking lot has been enlarged to make it easier for vehicles to enter and exit.  Parking is available for those with a valid NECC parking decal in Lot A.  Please be aware and use caution when entering and exiting Lot A.

Please note: Parking within the temporary construction fence are is prohibited. Any person(s) parking within the temporary construction fence area are liable to be towed at the owner’s expense.

Weekly Update: March 19, 2018

G&R Construction has put up a fence along the building, as well as around a small area inside Parking Lot A.  The Common St. entrance to the Dimitry parking lot will serve as the entrance and exit for this parking lot.

Currently, the opening is wide enough for only one vehicle to access at a time.  G&R Construction will soon be removing two sections of the fence in order to allow easier access; however, the curb cut for this opening is large enough to accommodate only one vehicle at a time.  This entrance/exit will be re-worked as part of the Dimitry project, but it is not scheduled until later in the construction project.

Weekly Update: March 12, 2018

G&R Construction will be putting up fences around the building beginning March 14, 2018. NECC staff, faculty, and students will no longer have access to the inside of the Dimitry Building. Also, beginning Wednesday, March 14, the entrance and exit to Dimitry Lot A will be shifted to Common St. There will be no available access via Franklin St.